WORKDAY.INTL in Google Sheets: Syntax & Examples

How-to basics · Updated November 23, 2026

The WORKDAY.INTL function in Google Sheets calculates the date that falls a specified number of working days before or after a given start date, letting you define which days of the week count as weekends and optionally exclude a list of holidays. Its syntax is WORKDAY.INTL(start_date, num_days, [weekend], [holidays]).

What Is WORKDAY.INTL and Why Does It Exist?

Google Sheets has a simpler WORKDAY function that assumes Saturday and Sunday are the weekend. That works for many people, but not for everyone. Some businesses operate Sunday through Thursday, some have a single weekend day, and some close on different days entirely. WORKDAY.INTL solves that by letting you specify exactly which days are non‑working. It also accepts a list of holiday dates, so you can exclude public holidays or company‑specific days off from the calculation.

The function is part of Google Sheets’ Date category and is the international variant of WORKDAY. It is particularly useful for project planning, HR leave calculations, invoice due dates, and any schedule that must skip non‑working days.

Syntax and Arguments Explained

The full syntax is:

WORKDAY.INTL(start_date, num_days, [weekend], [holidays])

  • start_date – the date from which to count. Must be a valid date reference (a cell containing a date, a date returned by another function, or a date entered as text in a recognized format).
  • num_days – the number of working days to add (positive) or subtract (negative). If you use a decimal, it is truncated to an integer.
  • [weekend] – optional. A number or a string that tells the function which days are weekends. If omitted, Saturday and Sunday are used (same as WORKDAY).
  • [holidays] – optional. A range or array of dates to exclude from the working‑day count.

The weekend argument can be a number from 1 to 17, each representing a different weekend pattern (e.g., 1 = Saturday/Sunday, 2 = Sunday/Monday, 7 = Sunday only, 11 = Monday only). You can also use a string of seven 0s and 1s, where 1 means a weekend day. For example, "0000011" means Saturday and Sunday are weekends (the first character is Monday).

How to Use WORKDAY.INTL: Step‑by‑Step Examples

Let’s walk through a few real examples. Assume cell A1 contains the date 2025-01-06 (a Monday).

Example 1: Standard Saturday/Sunday weekend

With start date in A1 and 10 working days to add:

=WORKDAY.INTL(A1, 10)

This returns 2025-01-20 (a Monday), because the 10 working days skip the two weekends in between.

Example 2: Sunday‑only weekend

If your weekend is just Sunday, use the weekend code 7:

=WORKDAY.INTL(A1, 10, 7)

Starting Monday Jan 6, adding 10 working days (skipping Sundays) lands on 2025-01-19 (a Sunday? Actually, let’s count: Jan 6 Mon, 7 Tue, 8 Wed, 9 Thu, 10 Fri, 11 Sat (working), 12 Sun (off), 13 Mon (1), 14 Tue (2), 15 Wed (3), 16 Thu (4), 17 Fri (5), 18 Sat (6), 19 Sun (off), 20 Mon (7), 21 Tue (8), 22 Wed (9), 23 Thu (10). So the result is 2025-01-23, a Thursday. Sorry, I miscounted – let’s be precise: with Sunday only as weekend, every day except Sunday counts. Starting Monday Jan 6, the 1st working day is Jan 6 itself? Actually, the function counts the start date as day 0, so the first working day after start is the next day that is not a weekend. So day 1 = Jan 7 (Tue), day 2 = Jan 8 (Wed), day 3 = Jan 9 (Thu), day 4 = Jan 10 (Fri), day 5 = Jan 11 (Sat), day 6 = Jan 13 (Mon, since Jan 12 is Sunday), day 7 = Jan 14, day 8 = Jan 15, day 9 = Jan 16, day 10 = Jan 17 (Fri). So the result is 2025-01-17. That is correct.

Example 3: Using a string for custom weekends

Suppose your weekend is Friday and Saturday. The string should have 1s for Friday and Saturday: Monday=0, Tuesday=0, Wednesday=0, Thursday=0, Friday=1, Saturday=1, Sunday=0, so "0000110".

=WORKDAY.INTL(A1, 10, "0000110")

This will skip Fridays and Saturdays, so the 10th working day from Jan 6 (Mon) is Jan 22 (Wed).

Example 4: Adding holidays

Put a list of holiday dates in cells C1:C3, e.g., 2025-01-01, 2025-01-20, 2025-02-14. Then:

=WORKDAY.INTL(A1, 10, 1, C1:C3)

If any of those holidays fall on a working day, they are skipped. In our example, Jan 20 is a holiday (Martin Luther King Jr. Day), so the 10th working day becomes Jan 21 (Tue) instead of Jan 20.

Choosing the Right Weekend Code

Google Sheets supports 17 predefined weekend codes. Here are the most common ones:

  • 1 – Saturday, Sunday (default)
  • 2 – Sunday, Monday
  • 3 – Monday, Tuesday
  • 7 – Sunday only
  • 11 – Monday only
  • 17 – Saturday only

If your weekend pattern isn’t in the list, use the string method. The string must be exactly 7 characters, each 0 (working day) or 1 (weekend), starting with Monday. For example, "1000001" means Monday and Sunday are weekends.

Common Errors and How to Fix Them

  • #VALUE! – Occurs if the start date is not a valid date, or if the weekend argument is not a valid number or string. Double‑check that the date is in a format Google Sheets recognizes (e.g., DATE(2025,1,6) or a cell with a date).
  • #NUM! – Occurs if the weekend number is outside 1–17, or if the string is not exactly 7 characters. Make sure the string has no extra spaces.
  • Holidays not being skipped – Ensure the holiday range contains actual dates, not text. If you typed dates as text, they won’t be recognized. Use DATE() or a cell formatted as a date.
  • Negative num_days – Works fine: =WORKDAY.INTL(A1, -5) returns the date 5 working days before the start date.

Comparing WORKDAY.INTL with WORKDAY and NETWORKDAYS.INTL

The plain WORKDAY function is the same as WORKDAY.INTL with weekend code 1 (Sat/Sun). It exists for backward compatibility and simplicity. If you only need the standard weekend, use WORKDAY – it’s shorter. But if you need a custom weekend, you must use WORKDAY.INTL.

There is also NETWORKDAYS.INTL, which counts the number of working days between two dates (instead of adding days). It uses the same weekend codes and holiday lists. For example, to count working days between Jan 1 and Jan 31 with Sunday only as weekend, you would use =NETWORKDAYS.INTL(DATE(2025,1,1), DATE(2025,1,31), 7).

Both functions are part of the same family and share the weekend/holiday logic, so once you understand one, the other is easy.

Frequently Asked Questions

Can I use a cell reference for the weekend argument?
Yes. The weekend argument can be a number or a string, and you can put that in a cell and reference it. For example, if B1 contains the number 7, then =WORKDAY.INTL(A1, 10, B1) works. If B1 contains the text "0000110", that also works.

Does WORKDAY.INTL count the start date as day 0 or day 1?
It counts the start date as day 0. The first working day after the start date is day 1. So if you want to include the start date as a working day, you would subtract 1 from num_days or use a different approach.

What happens if a holiday falls on a weekend?
The holiday is ignored if it falls on a day that is already a weekend. The function only skips holidays that occur on working days. So if you have a holiday on a Saturday and your weekend is Saturday/Sunday, it won’t affect the count.

Can I use WORKDAY.INTL to calculate a due date that must fall on a specific weekday?
No, WORKDAY.INTL always returns the date after the specified number of working days, which may be any weekday. If you need the next occurrence of a specific weekday, you would need a different formula, such as using WEEKDAY and MOD functions.

Is WORKDAY.INTL available in Excel?
Yes, Excel has a function with the same name and similar syntax, but the weekend codes are slightly different (Excel uses 1 for Saturday/Sunday, 2 for Sunday/Monday, etc., but the string method is the same). However, the function is available in Excel 2010 and later, while Google Sheets has had it for years.

Practical Tips and Limitations

  • Always use dates as actual date values, not text. If you type 1/6/2025 in a cell, Google Sheets usually converts it to a date, but if you use a formula, wrap it in DATE(2025,1,6) to be safe.
  • When using the string method, remember that the first character is Monday. A common mistake is to think it starts with Sunday.
  • The function ignores time values in the start date. Only the date part matters.
  • If you need to generate a list of working days, combine WORKDAY.INTL with SEQUENCE to create a series of start dates, then copy the formula down.
  • For international use, remember that holidays are not automatically recognized – you must provide them yourself.

WORKDAY.INTL is a powerful tool for anyone who needs to calculate dates based on non‑standard work weeks. Whether you’re scheduling shifts, tracking project milestones, or calculating delivery dates, it gives you full control over which days count as workdays.

Related

Try it: the Date Difference Calculator: days, months, years and weekdays between two dates, with the DATEDIF formulas.